Guide to the Car Wash
Construction Process
If you have decided to go into the car wash business by constructing a new car wash there are general steps that you can follow.
This is just a general guide that may help you with your planning. You do not necessarily need to follow these steps in exact order, but you may want to follow this order. You can move some steps up or down in the list. There will likely be some things that you will need to do that are not on this list; likewise, there may be some things on this list that you will not need do.
You can print this list and cross through each item as you complete
them. You can also write in additional things that you need or
want to do.
-
Start your written Business Plan. Open a word
processing document that you can keep open either on your computer
screen or in the background as you work on your car wash project.
Label your document "Business Plan". As you develop ideas
include them in this open document. Your Business Plan will
practically write itself.
-
Determine Your Objectives for your car wash construction
project
-
Decide on the type of car wash that you would like to
construct and operate.
- Estimate your Total Project Cost, including land.
Sample costs for various car washes:
6-bay ss car wash will cost about $400,000 to
500,000.
8-bay car wash about $500,000 to 600,000.
5- bay self-serve with single in-bay automatic.
$500,000 to $600,000
5-bay self-serve with two in-bay automatics
$700,000 to $900,000
Exterior-only conveyor $1,400,000
to $1,700,000
Conveyor automatic full-service or flex-service:
$1,500,000 to $1,800,000
Conveyor automatic
full-service with lube center: $2,100,000
- Judge Your Financial Ability to Fund the Project (pre-qualify yourself)
If you are new to the industry and you do not plan to offer collateral in addition to the car wash property you will need to make a cash down payment of about 20% to 23% of the Total Project Cost. Multiply the sample costs above times 20% to 23% to estimate your cash down payment.-
Determine the site selection characteristics that are common
for successful car washes of the type that you have decided to
construct.
-
Given that you can find a suitable site decide the general
area or areas where you would
like to construct your new car wash.
Note these areas in your business plan and why you have
chosen
them. Use the site selection guides provided by the equipment
manufacturers to help you narrow your site choices. For your
initial evaluation use the high end of each site selection factor.
For example, if the population range necessary for your chosen
type of car wash is 5,000 to 20,000 within a two-mile radius of the
site you may want to look only in those areas that offer 20,000 people
or more within two miles.
-
Find several specific potential
sites.
You may
want to check asking prices. Try to find land that is about the
size or only somewhat larger than the size of land that you will need.
In an urban or suburban area it is usually preferable that your
new car wash NOT be within a mile of any other car wash. It
usually preferable that
you not buy any more land than is necessary for just the car wash.
-
Taking into account the car wash site selection
characteristics and the competition, narrow your prospective sites to
just two or three serious candidates. You could even get
at least
a verbal agreement with one or more sellers.
-
Again estimate your project costs and determine whether you
will have enough cash down payment.
-
After you have determined that you will have the necessary
down payment and have identified viable sites contact us by telephone.
Call Alan Bussey, Car Wash Loans, at 817-267-4726. We
can
do a quick pre-qualification and quick pre-approval of your loan over
the telephone and by fax.
-
Once your have been pre-approved, complete your negotiations
verbally for your single specific car wash site.
Reach
verbal agreement.
- Prepare
a Letter of Intent and obtain written agreement from
the
seller.
-
Once you and land seller have reached agreement on a
sale/purchase price please contact us again to begin the formal
loan approval process .
-
Begin preparation of the written contract.
-
Make preliminary selection of equipment dealer.
- Draw
a preliminary/rough site plan yourself or obtain a
preliminary drawing from your/an equipment supplier. These
drawings
need to take into consideration any easements and setbacks.
-
Obtain a water, sewer, electric, and gas availability
letters
from the local utility authority. Determine the tap fees
and any
other related fees or deposits. If utilities are not already
available at the site determine the costs of bringing the necessary
utilities to the site.
-
Using your rough drawings visit the relevant zoning and
permitting offices to get a pre-approval of your zoning, conditional
use, and/or your construction permit. You may want to
carry with
you a plat of the site lot and surrounding lots.
- You
could meet with a local architect/engineer and your
equipment supplier to review the local building codes and the necessary
utility requirements.
- Get an estimate of the cost for all of the architectural work from several architects. Select and contract with an architect to develop the plans for construction.
- You
may want to enlist the help of a Civil Engineer to do a
Preliminary Site Plan and Floor Plan at this point. Often
the
architect will
subcontract with the suitable Civil, Mechanical, Electrical, and
Plumbing
Engineers. Discuss with your architect access to the Civil
Engineer.
-
Check zoning restrictions - get preliminary approval from
the relevant government. Before you check into zoning you
may
want to read the articles on zoning in the articles links elsewhere on
this web site
(CarWashLoans.com).
- If
a conditional use (or special use) permit is required get
an application process guide and a meeting schedule.
- Check
construction permitting process - get preliminary
approval.
- Check
for necessity for replatting -
get preliminary approval and timeline for formal approval.
- If you
haven't already done so, contact
us to start the formal loan approval process.
- Prepare
and sign the Contract for
Purchase for the land. Include reasonable conditions in your
contract.
-
Start the zoning change/condition use process.
-
Estimate your car wash building sizes. Consider
turning radii
and consider spacing between structures.
- It is
preferable if you will have a preliminary Site Plan
and Floor
Plan drawn by a civil engineer to make sure that you can build a large
enough structure for your intended car wash.
We can get your loan approved with just a Site Plan and Floor Plan , often combined onto one 11 inch x14 inch page. We do not need any drawings from an architect to get the loan approved. HOWEVER, many people who are confident that they will get the loan, go ahead and get the engineering and architecture work essentially done so that they can get started on the zoning and permitting process.
IF you need to apply for a zoning change or for a conditional use
permit (special use permit) you may want to have more of the
architectural drawings done, probably at least the Floor Plan and the
Elevations, for your presentations. Check with your engineer,
architect, the zoning office, and the construction permitting office.
You will NOT likely need at this time the plumbing, electrical,
and mechanical.
- Receive
formal loan approval in the form of a written
Conditional Commitment Letter.
- Finalize
equipment order.
- After
your loan is approved have the Architect and/or
Engineer(s) complete the set of construction plans.
- Submit
plans and specifications to city for and construction
permits if you have not already done so.
- Submit
plans and specifications to prospective construction
contractors for construction bidding.
- Select,
or at least preliminarily select, a construction
contractor.
-
After your loan is approved your lender will provide to you
with a Commitment Letter for your signature. At this time
the
lender will ask you for a check to pay for the Appraisal, the
Environmental Survey, and any other necessary third-party work.
This check is normally for between $6,000 to $8,000, depending
upon your specific project requirements.
-
Once you have accepted the lender's commitment letter and
paid your deposit the Construction Management Department representative
(or similar) will provide to you and to your contractor a checklist for
the information and documents that are required to be provided by the
contractor. The lender usually requires that the
construction
contract and other important documents be prepared using the AIA
forms.
-
The Loan Closing Coordinator (or similar) will provide to
you with
a Closing Checklist for the information and documents not otherwise
required from the contractor. This includes information on
the
car wash hazard and liability insurance and personal life insurance on
the guarantors,
when required.
-
After your loan is approved and the lender has received your
deposit the lender will select and formally contract with a appraiser
who is already on their list of pre-approved appraisers and will
contract with an environmental firm to conduct an environmental study
on the property (if necessary). Do
not engage an appraiser or an environmental firm directly, this is the
lender's
responsibility.
-
The Construction Management Department representative will
provide a copy of your plans and specifications to the 3rd-party
Construction Management Company (or similar) to review the plans to
confirm that the project can be completed within your planned budget
and approved loan.
-
Select construction contractor, if you have not already done
so.
-
Third-party reports will be ordered by the lender:
appraisal according to plans and specifications, and a Phase I
environmental report.
- Complete
platting process, if necessary.
- Sign
contract with the construction contractor. Use
AIA forms
and other forms as specified by the lender.
- Complete
the construction permitting process.
- Receive
appraisal report. This will be reviewed by the
lender's appraisal review personnel.
-
Have plans and specifications reviewed by the lender's
3rd-party construction oversight company.
- Close the loan and the purchase of the land.
- Start
construction.
- Complete
construction and install the car wash equipment.
-
Utilities turned on and car wash equipment started up and
adjusted.
- Obtain
Certificate of Occupancy.
- Open
your car wash for business.